House Raising Cost in Brisbane (2026)
Updated 2026-09-04 · Register QBCC
Raising a Queenslander and building a new level in underneath is close to a Brisbane-only renovation, and people searching for its cost are usually deciding between raising, extending outwards, and moving. The range below is the observed Greater Brisbane figure for the whole job in 2026. What a range cannot tell you is the part that actually decides whether the project happens and what it lands at: whether Council treats your raise as accepted development or as an application, how high a flood level forces you to lift, which QBCC licence class covers each half of the work, and what a builder is legally allowed to ask for before anyone turns up. This guide covers those four, and names the section of the instrument each rule comes from so you can check it rather than take it.
Costs at a glance
Ranges reflect quotes observed locally — not national averages, not advertised "from" prices.
| Service | Typical range (A$) |
|---|---|
Raise and build in under a Queenslander (raise house + new lower level) Based on Abode Construction's Brisbane raise-and-build-under guide (QBCC 15139300, updated August 2026), which puts a mid-range Queenslander lift and build-under at $280,000–$480,000 and the lift alone at $45,000–$90,000; premium projects run $600,000–$1.2M+. Varies with block slope, ceiling height gained, and re-routing services. | A$250,000 — A$500,000 |
Two approvals, and only one of them is Council's
Planning approval and building approval are separate decisions made by different people, and a raise needs the second one whatever the answer to the first is. Brisbane City Council states plainly that you need building approval before starting work on extensions, raising and renovations, and directs you to contact a licensed building certifier — in Queensland that is normally a private certifier you engage yourself, not a council officer.
On the planning side, the question is whether your site sits in the Traditional building character overlay, which covers a large share of Brisbane's pre-1946 housing. Council lists, among the minor building work that may not need planning approval in that overlay, both "enclosing under an existing building" and "raising a house where the new height does not exceed 9.5 metres". The catch is the definition of minor building work: City Plan's administrative definitions (schedule 1, table SC1.2.2.B) define it as building work that increases a building's gross floor area by no more than the lesser of 50 m² and an area equal to 5% of that gross floor area. Raising adds no gross floor area at all, so for the lift itself the 9.5 m height is the test. A full new lower level adds far more than either limit, so the build-under half generally falls outside that exemption and is assessed against the Traditional building character (design) overlay code, plus the (demolition) overlay code where the work involves demolition. Council's own summary of the overlay is that you will generally need planning approval for external extensions. On one project, then, the raise can be accepted development while the room underneath is an application — that is not a contradiction, it is two different tests. Check table 5.3.4.1 Prescribed accepted development for your address, and note that a neighbourhood plan area can add criteria on top.
On the building side the rules come from the Queensland Development Code. For an extension or renovation to an existing house, Council names MP 1.2 — Design and siting standards for single detached housing on lots 450 m² and over — and MP 1.1 for lots under 450 m². A separate part, MP 1.4 — Building over or near relevant infrastructure, is the one written for work over or near a sewer or water main, and it is worth raising with your certifier early: footings for a new lower level go into ground the old stumps never reached.
Why the lift height is usually set by a flood level, not by you
Brisbane City Council sets a minimum habitable floor level (MHFL) for property: the minimum level, in metres AHD, at which habitable areas of a development must be constructed. Council's own definition of a habitable area generally includes bedrooms, living rooms, kitchen, study, family and rumpus rooms. That one number, not your floor plan, decides whether the space you gain underneath can be bedrooms or has to be garage, laundry and storage.
Which flood the level comes from depends on the source. Council's defined flood event is the 1% AEP flood for creek and waterway flooding, the 2% AEP flood for overland flow, and the Residential Flood Level for Brisbane River flooding. The document that carries your property's levels for building and development purposes is the FloodWise Property Report; Council states explicitly that the Flood Awareness Map is for awareness only and does not guide planning or development applications, which is worth knowing because the two look similar. If your block is a Large Allotment or sits in an overland flow path, Council says it cannot supply an accurate MHFL for design purposes and recommends a Registered Professional Engineer of Queensland determine it.
The practical consequence is that on a flood-affected block the lift height is an output, not a choice: the new floor either sits at or above the MHFL or the rooms below change use. That flows straight into the quote — how far the house goes up drives stair runs, stump and post lengths, how much of the services run has to be re-routed, and whether the street elevation still passes the character overlay. The Queensland Development Code part written for this situation is MP 3.5 — Construction of buildings in flood hazard areas. Get the FloodWise report before you brief a designer, not after the drawings exist.
There is no house-raising licence — and that is the useful part
Schedule 2 of the Queensland Building and Construction Commission Regulation 2018 lists every class of contractor's licence, and none of them is house raising, restumping or house removal. Raising a Queenslander and building in underneath is building work on a class 1 building, and the scope of work for Builder — low rise begins "Building work on a class 1 or class 10 building" (sch 2 pt 4 s 2(1)) with no floor-area limit attached to it. The 2,000 m² gross floor area cap in the next subsection applies to classes 2 to 9, and the three-storey limit people quote at you belongs to Builder — medium rise. For this job a low-rise builder is not a lesser builder and there is nothing to upgrade to.
What that licence does not carry is the work with its own class. Schedule 1 s 2 excludes work of $3,300 or less from needing a licence, but not where the work falls within the scope of certain classes, whatever it is worth — among them building design (sch 2 pts 11 to 13), plumbing and drainage (pt 18), drainage (pt 19), gasfitting (pt 36), site classifier (pt 51) and termite management — chemical (pt 56). A raise touches most of that list, so the familiar "$3,300 or more needs a licence" shorthand answers almost nothing here. Site classification is the one to notice: it is licensed at any value, and on Brisbane's reactive clay the site class is what the new footing design is built on.
Two more classes turn up as subcontractors. Foundation work (piling and anchors), sch 2 pt 35, covers excavating and installing support, underpinning, piling and site dewatering — routine on a sloping block. Carpentry, pt 16, covers erecting subfloor framing. None of this changes who your contract is with; it changes what to ask. Take the licence number, check the class on the QBCC register, and ask which licence covers the drainage and which covers the termite system before day one rather than after.
A raise is a level 2 regulated contract — what that gives you
Any domestic building contract priced at or above $20,000 is a level 2 regulated contract — the QBCC Regulation 2018 s 45 prescribes $20,000 as the level 2 amount — so every raise-and-build-under is one. The contract must be in writing, dated and signed, and must state the contractor's name as it appears on the licence, the licence number, a description of the work, the plans and specifications including those required to carry out the work under any development approval, the start date, the date for practical completion, the statutory warranties, and a conspicuous notice of your right to withdraw (QBCC Act 1991 sch 1B s 14).
The money rules are the ones to memorise. On a level 2 contract the deposit is capped at 5% of the contract price; 10% is the level 1 figure, which covers regulated contracts priced between $3,300 and $20,000 (sch 1B s 6 sets that floor), and 20% applies only where more than half the contract price is off-site work (sch 1B s 33). After that, a progress claim must be directly related to the progress of the work at the building site and proportionate to the value of the work done (s 34) — so the payment schedule should track the stages below, not the calendar. You have five business days to withdraw after receiving your signed copy of the contract (s 35), and the contractor must give you a commencement notice within ten business days of starting on site (s 16).
Warranty cover attaches to the job, not to the licence, and the threshold is the regulated amount, which the QBCC Act defines as $3,300 (s 67WC(3)). Support-structure work sits squarely inside the scheme: the Regulation prescribes building work for the installation, repair or replacement of support structures for a residence as primary insurable work, and gives replacement of a stump as its worked example (s 27(f)). QBCC's own A-Z guide of insurable building work states that restumping over $3,300 is primary insurable work, with premium payable on the whole contract value. A raise quoted with no premium line is a raise with no cover.
The order of work, and the two approvals people find out about late
The sequence on a raise is fairly fixed, and it is worth knowing because your progress payments have to track it. Site classification and engineering come first, then the approvals; then the house is jacked and held on temporary supports; then the new stumps, posts or piers and their footings go in; then the lower floor slab or framed floor; then framing and enclosing the new level; then services; then termite management; then linings and finishes. Anything that changes the lift height — a flood level, an overlay condition — has to land before the engineering, because it changes every stage after it.
The plumbing approval catches people out because the category is defined by exclusion. The Plumbing and Drainage Act 2018 s 6 splits plumbing and drainage work into permit work, notifiable work, minor work and unregulated work; the Plumbing and Drainage Regulation 2019 s 4 then defines permit work as any plumbing or drainage work that is not one of the other three. Schedule 1 part 2 of that Regulation lists what is notifiable, and most of a build-under's plumbing is on it. Item 3 covers extending, altering, replacing or removing sanitary plumbing for an existing building, with no building-class limit at all. Items 4 and 9 are narrower: sanitary drainage other than a combined sanitary drain, and installing or relocating a fixture, each for an existing class 1 or 10 building or structure, an extension to an existing class 1 building, or a structure for one. Notifiable work is lodged by your licensed plumber after the fact; permit work needs a permit issued before it is carried out, and carrying it out without one is an offence (Act s 66). Part 1 of that schedule pulls work back out of notifiable where it involves a combined sanitary drain, trade waste, or a performance solution. Ask your plumber in writing which category your job falls into.
Termite management is the other one. Under the NCC 2022 Housing Provisions Part 3.4, a termite management system for a class 1 building must comply with AS 3660.1 (or be tested to section 5 of AS 3660.3), and a durable notice must be permanently fixed to the building in a prominent location recording the system installed, the date, the life expectancy of any chemical, and the inspection recommendation. That notice is the thing to ask for at handover: it is the only part of the termite system you can see afterwards. Note that chemical termite management is a licensed class at any value (QBCC Regulation 2018 sch 2 pt 56), so it should appear as its own line with its own licence number.
Common questions
Does raising my house need Council planning approval?
It depends which half of the job you mean, and whether you are in the Traditional building character overlay. Council lists raising a house where the new height does not exceed 9.5 metres among the minor building work that may not need planning approval in that overlay, and raising adds no gross floor area, so the height is the test for the lift. The new level underneath is different: City Plan defines minor building work as building work that increases gross floor area by no more than the lesser of 50 m² and 5% of the building's gross floor area, and a habitable lower level is normally well past that, so it is assessed against the overlay codes. A neighbourhood plan can add criteria. Building approval, from a licensed building certifier, is required either way.
Can the new lower level have bedrooms in it?
Only if its floor is at or above the minimum habitable floor level Council sets for your property. Council defines that as the minimum level in metres AHD at which habitable areas must be constructed, and its definition of habitable areas generally includes bedrooms, living rooms, kitchen, study, family and rumpus rooms. Get the level from a FloodWise Property Report — the Flood Awareness Map is explicitly not for development purposes. If your block is a Large Allotment or in an overland flow path, Council says it cannot supply an accurate level and recommends a Registered Professional Engineer of Queensland determine it. Below the level, the space is garage, laundry and storage.
Which QBCC licence class should the builder hold?
For the raise and the build-under together, Builder — low rise is the right class: its scope of work is building work on a class 1 or class 10 building, with no floor-area cap (QBCC Regulation 2018 sch 2 pt 4 s 2(1)). There is no separate house-raising or restumping class in schedule 2. The 2,000 m² cap applies to classes 2 to 9 and the three-storey limit belongs to Builder — medium rise, so neither restricts a house. Then check the pieces that carry their own class at any value — building design, plumbing and drainage, drainage, gasfitting, site classifier, and chemical termite management (sch 1 s 2).
How much deposit can a builder ask for on a raise?
Five per cent of the contract price. A raise-and-build-under is priced above the $20,000 level 2 amount set by QBCC Regulation 2018 s 45, which makes it a level 2 regulated contract, and schedule 1B s 33 of the QBCC Act caps the deposit on one at 5%. The 10% figure applies to level 1 contracts, priced between $3,300 and $20,000, and 20% only where off-site work is more than half the contract price. Every later payment must be directly related to progress at the site and proportionate to the work done (s 34). You also have five business days after receiving your signed copy to withdraw (s 35).
Sources & when we checked them
- ·Brisbane City Council — Extensions, raising and renovations (raising to no more than 9.5 m and enclosing under listed as minor building work in the Traditional building character overlay; building approval from a licensed building certifier; QDC MP 1.1 and MP 1.2 named for extensions to an existing house) (checked 2026-09-04)
- ·Brisbane City Plan 2014, schedule 1 (table SC1.2.2.B, administrative terms and definitions), version 19 of 1 May 2020 — minor building work: "building work that increases the gross floor area of a building by no more than the lesser of the following— 50m2; an area equal to 5% of the gross floor area of the building". This is the most recent version of the definitions we could retrieve; City Plan online, which carries the current version, blocks automated access. The 2016 version 2 text of the same term was worded differently ("an alteration, addition or extension … where the floor area including balconies is less than five per cent of the building or fifty square metres, whichever is the lesser"), so check the current version for your own application. (checked 2026-09-04)
- ·Brisbane City Council — Glossary of flood terms (minimum habitable floor level in metres AHD and what counts as a habitable area; defined flood event of 1% AEP for creek/waterway, 2% AEP for overland flow and the Residential Flood Level for Brisbane River; FloodWise Property Report guides building and development while the Flood Awareness Map does not; RPEQ engineer where no accurate level can be supplied) (checked 2026-09-04)
- ·Queensland Building and Construction Commission Regulation 2018 (current as at 1 September 2026) — sch 2 pt 4 (Builder — low rise scope: class 1 or class 10 building, 2,000 m² cap applying to classes 2–9), pts 11–14, 16, 18, 19, 35, 36, 51, 56; sch 1 s 2 (the $3,300 exclusion and the classes it does not reach); s 27(f) (support structures as primary insurable work, example: replacement of a stump); s 45 (level 2 amount of $20,000) (checked 2026-09-04)
- ·Queensland Building and Construction Commission Act 1991 (current as at 1 February 2026) — s 67WC(1) and (3) (primary insurable work; regulated amount of $3,300); sch 1B ss 6, 7 (level 1 and level 2 regulated contracts), 14 (contract requirements), 16 (commencement notice), 33 (deposit caps of 5%, 10% and 20%), 34 (progress payments proportionate to work at the site), 35 (five business day withdrawal) (checked 2026-09-04)
- ·QBCC — A-Z guide of insurable building work, July 2024 (restumping over $3,300 is primary insurable work, premium payable on the whole contract value; underpinning likewise, citing Regulation s 27(f)) (checked 2026-09-04)
- ·Plumbing and Drainage Act 2018 (current as at 1 February 2026) — s 6 (the four categories of plumbing and drainage work), s 66 (a permit is required before permit work is carried out, maximum penalty 250 penalty units) and s 83 (after notifiable work is finished: notice in the approved form and the prescribed fee to the commissioner within 10 business days, and a copy of that notice with an explanatory statement to the occupier or the person who asked for the work within 20 business days, maximum penalty 60 penalty units each) (checked 2026-09-04)
- ·Plumbing and Drainage Regulation 2019 (current as at 2 January 2026) — s 4 (permit work defined as work that is not notifiable, minor or unregulated), s 10 (QDC MP 3.5 — Construction of buildings in flood hazard areas), sch 1 pt 1 (combined sanitary drain, trade waste and performance solutions excluded from notifiable work) and sch 1 pt 2 items 1, 3, 4 and 9 (notifiable work: sanitary plumbing for an existing building of any class at item 3; sanitary drainage other than a combined sanitary drain, and installing or relocating a fixture, for an existing class 1 or 10 building or an extension to an existing class 1 building, at items 4 and 9) (checked 2026-09-04)
- ·National Construction Code 2022, Housing Provisions Part 3.4 — Termite risk management (a termite management system for a class 1 building complies with AS 3660.1 or is tested to section 5 of AS 3660.3; a durable notice permanently fixed in a prominent location stating the system, date, chemical life expectancy and inspection recommendation) (checked 2026-09-04)
- ·Business Queensland — Queensland Development Code (part titles: MP 1.1 and MP 1.2 design and siting standards for single detached housing under and over 450 m²; MP 1.4 building over or near relevant infrastructure) (checked 2026-09-04)